Structural Safety Assessment & Reinforcement for PV Integration on Light Steel Portal Frame Workshops

22 June, 2026

How to Achieve Perfect Integration Between Steel Structure Factory Roofs and PV Systems?

I. Introduction

1. Background
Light‑weight steel portal frames are widely used in industrial workshops. Their roofs, being large in area and largely free of obstructions, make ideal platforms for rooftop photovoltaic (PV) installations.

2. Core problem
Most existing portal‑frame workshops were not originally designed for the extra dead load imposed by PV modules (about 0.15 kN/m²). Furthermore, many such workshops have been in service for years and suffer from corrosion, aging, and various detailing deficiencies.

3. Main argument
Any PV addition must follow the strict sequence: first inspect and appraise, then verify by recalculation, and finally strengthen before construction. Ensuring the structural safety is the prerequisite for a long‑term, reliable operation of the PV system.

II. Phase 1 – Preliminary inspection and assessment: establishing the actual condition of the structure

When original drawings are missing or incomplete, on‑site inspection becomes the basis for all subsequent calculations. The inspection and assessment shall be carried out in accordance with GB/T 50344 Standard for Inspection of Building Structures.

1. Verification of structural system and geometric parameters

Structural form: confirm the column‑base connection type (rigid or pinned) and the layout of the roof bracing system.

Member sizing: measure the cross‑sectional dimensions and plate thicknesses of steel columns, beams, and purlins, and check them against the design drawings (if available).

Deformation survey: use a level or total station to measure beam deflections and column verticality deviations.

2. Testing of mechanical properties of materials

Steel grade: determine the actual strength grade (e.g., Q235, Q355) by Leeb hardness testing or by taking tensile coupons.

Corrosion assessment: inspect coating thickness and the extent of corrosion, and evaluate how much the section has been reduced.

3. Investigation of connections and constructional details

Joint quality: check high‑strength bolted connections and welds; use ultrasonic testing to detect internal weld defects.

Bracing integrity: verify that roof bracing, column bracing, and knee braces are present and in good condition.

4. Survey of loads and service history

Existing loads: determine the current roof loads (e.g., suspended loads, dust accumulation).

Past modifications: find out whether the workshop has suffered fire damage or undergone any extension or alteration.

III. Phase 2 – Structural verification by calculation: quantifying the available capacity margin

With the inspection data, a structural model is built to check the load‑bearing capacity and to decide whether the existing frame can accommodate the added PV system.

1. Load values and combinations

Additional dead load: self‑weight of PV panels and mounting frames, typically about 0.15 kN/m² for flat layouts; actual values shall be taken from the manufacturer’s data.

Wind load: portal frames are wind‑sensitive. Wind pressure coefficients shall be determined according to GB 51022‑2015 Technical Code for Steel Structure of Light‑Weight Buildings with Gabled Frames, with special attention to suction at roof edges. Under the new code, the calculated wind load standard value is multiplied by 1.1 for the main frame and by 1.7 for purlins and secondary members.

Snow load: use the 100‑year return‑period value, which is more conservative than the previous 50‑year requirement.

Load combinations: consider both ultimate and serviceability limit states.

2. Items to be checked

Purlins: strength, stability, and deflection – these are often the weakest link and require the most careful scrutiny.

Main frame: strength and in‑plane / out‑of‑plane stability of beams and columns.

Connections: capacity of beam‑to‑column joints, column bases, and purlin supports.

Foundations: effect of the additional loads on the bearing capacity of the foundation and subsoil.

3. Grading of the assessment conclusions

Based on the verification results, the structure is classified into one of two categories:

Compliant: the PV system can be installed directly.

Non‑compliant: strengthening measures must be undertaken.

IV. Phase 3 – Strengthening design: targeted measures to increase capacity

On the basis of the assessment conclusion, the strengthening design shall follow GB 51367‑2019 Standard for Design of Steel Structure Strengthening. The strengthening approaches can be divided into member‑based strengthening and system‑level modification (changing the load path).

1. Purlin Reinforcement Methods

Reinforcement MethodTechnical PrincipleApplicable ScenarioFeatures
Add extra knee bracesReduce the out-of-plane calculation length of purlins to prevent lower flange instabilityPurlin stability fails to meet standard requirementsEasy construction, low cost, no damage to roof waterproofing
Cross-section enlargementWeld angle steel or channel steel to the lower flange of purlinsInsufficient strength and stiffnessImproves section modulus for bending, but increases self-weight
Change simply-supported purlins to continuous onesAdd connecting plates at supports to form continuous force-bearing purlinsExcessive mid-span bending momentReduce mid-span moment by utilizing negative support moment
Add mid-span support pointsInstall struts at purlin mid-span to shorten calculation spanExcessive deflectionObvious stress improvement, support layout design required

2. Steel Beam (Portal Frame Beam) Reinforcement Methods


Reinforcement MethodTechnical PrincipleApplicable ScenarioFeatures
Cross-section enlargementWeld steel plates to beam lower flange or webInsufficient bearing strengthWeld T-section steel or plates to upgrade bending capacity
Install triangular trussesSet triangular trusses or inclined supports under beamsInsufficient bearing capacity of long-span beamsCreate a new force transmission system to greatly cut mid-span bending moment
Densify knee bracesShorten the out-of-plane calculation length of beam lower flangeOverall beam stability fails to meet standard requirementsReduce mid-span bending moment by utilizing negative support moment


3. System conversion method – an innovative strengthening approach

To overcome the difficulties and long construction time associated with traditional strengthening methods, the system conversion method offers an alternative. By adding triangular trusses or inclined struts to the portal frame beams, or by installing longitudinal girders between main beams, the load‑transfer path of the original structure is altered. In this way, the additional PV loads are transmitted through the new system, thereby increasing the overall bearing capacity. This approach minimises disturbance to the existing structure.

V. Phase 4 – Strengthening construction: quality control and safety assurance

Construction is the critical step where the strengthening design is realised on site, and strict quality control must be exercised throughout.

1. Preparation for construction

Temporary supports: during strengthening works, the existing structure may be in its most unfavourable state; temporary supports shall be erected to ensure safety.

Surface preparation: rust removal and grinding are required on the areas to be strengthened.

2. Control of key construction procedures

Welding quality: strengthening welds must meet the design requirements and shall be subject to non‑destructive testing.

Bolted connections: high‑strength bolts shall be tightened to the specified torque and checked accordingly.

Corrosion protection: after strengthening is completed, all exposed steel surfaces shall be given anti‑corrosion coatings.

3. Safety monitoring during construction

Concentrated stacking of materials on the roof shall be avoided, and overloading during construction is strictly prohibited.

Work at height requires safety nets to prevent falls.

VI. Phase 5 – Operation, maintenance and monitoring: ensuring long‑term safety

Once the PV system is commissioned, long‑term performance monitoring of the structure remains equally important.

1. Regular inspections

Visual inspection: check for obvious deformations, corrosion, and loose connections at joints.

Waterproofing inspection: examine the connections between PV supports and the roof membrane for any signs of leakage.

2. Structural health monitoring

For critical workshops, a structural health monitoring (SHM) system may be installed to provide real‑time data on:

Stress and strain: stress variations in key members.

Deflection: roof deformation under wind and snow loads.

Vibration characteristics: changes in natural frequencies, which indicate any degradation in structural stiffness.

3. Periodic re‑assessment

It is recommended that a comprehensive structural safety re‑assessment be carried out every 3 to 5 years. In particular, inspections should be performed promptly after extreme weather events, such as typhoons or heavy snowstorms.

VII. Conclusions and recommendations

1. A full closed‑loop process: the addition of PV systems to portal‑frame workshops must follow a complete technical cycle: inspection → verification → strengthening → construction → operation and maintenance.

2. Mandatory code compliance: since the implementation of the new national standard GB 51022‑2015 Technical Code for Steel Structure of Light‑Weight Buildings with Gabled Frames, the design values for wind and snow loads have become more stringent. Installing PV without adequate strengthening not only poses legal risks but also creates serious safety hazards.

Online Message

8615621008853

8615621008853

danielho@jxsteelstructure.com

0

skype:

wechat qrcode
wechat qrcode